Payroll Upgrade and Integration

Payroll Upgrade: Upgrade was completed and went live in Jan 2014, Post Production Support completed, and April 2014 payroll run was completed on the R12 instance.

b. Payroll Integration with GIFMIS: User Acceptance Test has been completed; deployment on production has started from April 28 2014, and fully integrated system to go-live on June 2 2014. The next stages are: conduct Stress Test using GES Payroll Data (should have been completed by March 2014). However, significant delay is expected, since it needs about 18 runs and each run takes about 2 weeks. Furthermore, there is an accumulation of data to be run due to the fact that GES has not been run for months and about 89% of GES data is resident on the Payroll.